Roads20IB0024

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT. TAFT -ORAS - SAN POLICARPO- ARTECHE ROAD, K0904+228 - K0904+327, K0947+505 - K0947+569, K0956+100 - K0956+427, K0956+683 - K0956+773, K0962+737 - K0963+000, JCT

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT. TAFT -ORAS - SAN POLICARPO- ARTECHE ROAD, K0904+228 - K0904+327, K0947+505 - K0947+569, K0956+100 - K0956+427, K0956+683 - K0956+773, K0962+737 - K0963+000, JCT is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱10,308,601.74. Status: Reported complete (DPWH). Contractor on record: YFL BUILDERS. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Wright-Taft-Borongan Road, K0897+000-K0898+000, Brgy. San Isidro, Sulat, Eastern Samar
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Eastern Samar DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱10,308,601.74

Progress

Reported complete (DPWH)

Start Date

February 20, 2020

Target End

July 18, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.