Roads23OD0219

CONSTRUCTON OF ROADS AND DRAINAGE, BRGY. 32 PHASE 2, CLAOOCAN CITY

CONSTRUCTON OF ROADS AND DRAINAGE, BRGY. 32 PHASE 2, CLAOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱9,560,924.06. Status: Reported complete (DPWH). Contractor on record: ELITE GEN CONTRACTOR AND DEVELOPMENT CORP. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23OD0219 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-11-03 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTON OF ROADS AND DRAINAGE, BRGY. 32 PHASE 2, CLAOOCAN CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Bank of Creeks in Phase 7, Brgy. 176, Caloocan City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

121 projects · ₱7.5B total · 3 flags

Other projects by this contractor

Construction of Road Dike along Bucayao River (East Side), Sitio Malinao Section, Barangay Tagumpay, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱247.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO (DOWNSTREAM), SAN JOSE, OC

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, VILLAFLOR SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱213.9M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, CANLASID SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)

Construction of Road Dike along Mag-asawang Tubig River, Sitio Dike, Barangay Apitong Section, Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY HINOLASO, DOLORES, EASTERN SAMAR

Region VIII, Region VIII

2024₱190.9M
Past target date (DPWH On-Going)
View all 121 projects →

4. Implementation

Contract Amount

₱9,560,924.06

Progress

Reported complete (DPWH)

Start Date

June 19, 2023

Target End

November 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of CaloocanBarangay 32
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.