Construction of Revetment22OC0184

Improvement of Slope Protection of Sapang Buwaya Creek Near Annex 31 Subdivision (Phase VII), Brgy. Marcelo Green, Parañaque City

Improvement of Slope Protection of Sapang Buwaya Creek Near Annex 31 Subdivision (Phase VII), Brgy. Marcelo Green, Parañaque City is a DPWH-tracked public work in CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region. Reported contract value: ₱48,993,324.65. Status: Reported complete (DPWH). Contractor on record: RAICON DEVELOPMENT CORP FORMERLY : RA IGNACIO CONST CORP / P L G L CONST. Figures trace to sumbong.

CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall (Phase 2), Villa Maria, Brgy. 168, Caloocan City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003128

₱703,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003020

₱287,986,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001728

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0007225

₱945,393.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009235

₱270,626.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,993,324.65

Progress

Reported complete (DPWH)

Start Date

June 22, 2022

Target End

February 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.