Roads20CE0105

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - BONGABON - RIZAL - AURORA RD - K0148+320 - K0150+521, K0151+540 - K0152+536

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS - BONGABON - RIZAL - AURORA RD - K0148+320 - K0150+521, K0151+540 - K0152+536 is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱27,822,115.82. Status: Reported complete (DPWH). Contractor on record: SYMMETRICON BUILDERS CORP. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Brgy. Puncan, Carranglan (along Talavera River), Nueva Ecija
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Nueva Ecija 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

61 projects · ₱508.4M total · 1 flags

4. Implementation

Contract Amount

₱27,822,115.82

Progress

Reported complete (DPWH)

Start Date

December 2, 2020

Target End

April 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.