Buildings and Facilities23O00063

CONSTRUCTION OF OTHER BUILDING ESTABLISHMENT OF THE NBI FACILITY (INCLUDING CIVIL WORKS) OF NBI BUILDING IN TAFT AVENUE, ERMITA, MANILA

CONSTRUCTION OF OTHER BUILDING ESTABLISHMENT OF THE NBI FACILITY (INCLUDING CIVIL WORKS) OF NBI BUILDING IN TAFT AVENUE, ERMITA, MANILA is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱28,269,494.46. Status: Past target date (DPWH On-Going). Contractor on record: WAY MAKER GEN CONTRACTOR OPC. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱28,269,494.46

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2024

Target End

August 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.