Buildings and Facilities21OC0178

CONSTRUCTION/COMPLETION OF 4STY32CL, COL. E. DE LEON ELEMENTARY SCHOOL, PARAÑAQUE CITY, METRO MANILA

CONSTRUCTION/COMPLETION OF 4STY32CL, COL. E. DE LEON ELEMENTARY SCHOOL, PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱10,000,000.00. Status: Reported complete (DPWH). Contractor on record: GOLDEN 3T CONST CORP FORMERLY:GOLDEN 3T CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Flood Control Wall along Marulas - Gen. T. de Leon Creek (Phase 2), Barangay Marulas, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Metro Manila 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱524.8M total · 0 flags

4. Implementation

Contract Amount

₱10,000,000.00

Progress

Reported complete (DPWH)

Start Date

October 14, 2021

Target End

February 10, 2022