Roads20AB0088

OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS, PINILI-NUEVA ERA ROAD, K0454+432 - K0454+932

OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS, PINILI-NUEVA ERA ROAD, K0454+432 - K0454+932 is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱7,350,000.00. Status: Reported complete (DPWH). Contractor on record: CURRIMAO INTEGRATED BUILDERS CORP. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱19,699,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Ilocos Norte-Apayao Road, K0503+034 - K0503+987, Dingras, Ilocos Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,350,000.00

Progress

Reported complete (DPWH)

Start Date

October 12, 2020

Target End

February 28, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.