Roads18AD0046

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROAD AND BRIDGES - CONSTRUCTION OF CANDON -BANAYOYO CIRCUMFERENTIAL ROAD (FROM JCT.MNR TABLAC TO BANAYOYO NATIONAL HIGHWAY)

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROAD AND BRIDGES - CONSTRUCTION OF CANDON -BANAYOYO CIRCUMFERENTIAL ROAD (FROM JCT.MNR TABLAC TO BANAYOYO NATIONAL HIGHWAY) is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱37,161,328.65. Status: Reported complete (DPWH). Contractor on record: FIRST NORTHWAY DEVELOPMENT. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Paras-Paypayad-Oaig-Daya Flood Control Candon City, Ilocos Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033578

₱0.00 · FY2018

Released to Division of Ilocos Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱37,161,328.65

Progress

Reported complete (DPWH)

Start Date

February 19, 2018

Target End

September 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.