CONSTRUCTION OF ABACA PROCESSING BUILDING/FACILITY, MARIHATAG, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 1st DEO, Region XIII. Reported contract value: ₱3,959,184.65. Status: Reported complete (DPWH). Contractor on record: MELROSHEAN CONST CORP. Figures trace to dpwh.

Surigao del Sur 1st DEO, Region XIII
Region: Region XIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,959,184.65

Progress

Reported complete (DPWH)

Start Date

November 17, 2020

Target End

June 14, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.