Bridges17J00077

WIDENING OF MANICAHAN BRIDGE (B00574MN) ALONG PAGADIAN - ZAMBOANGA CITY ROAD, P00117212MN, ZAMBOANGA CITY, BEG. OF PROJ.: 1915+740.00, ABUTMENT A: 1915+758.00, ABUTMENT B: 1915+848.84, END OF PROJ.: 1915+870.00, APPROACHES NET LENGTH: 39.16 LN.M., BRIDGE

WIDENING OF MANICAHAN BRIDGE (B00574MN) ALONG PAGADIAN - ZAMBOANGA CITY ROAD, P00117212MN, ZAMBOANGA CITY, BEG. OF PROJ.: 1915+740.00, ABUTMENT A: 1915+758.00, ABUTMENT B: 1915+848.84, END OF PROJ.: 1915+870.00, APPROACHES NET LENGTH: 39.16 LN.M., BRIDGE is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱107,551,634.49. Status: Past target date (DPWH On-Going). Contractor on record: BENDIMIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17J00077 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    96% reported · imagery 2016-01-25 → 2025-10-16

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: WIDENING OF MANICAHAN BRIDGE (B00574MN) ALONG PAGADIAN - ZAMBOANGA CITY ROAD, P00117212MN, ZAMBOANGA CITY, BEG. OF PROJ.: 1915+740.00,  ABUTMENT A: 1915+758.00, ABUTMENT B: 1915+848.84, END OF PROJ.: 1915+870.00, APPROACHES NET LENGTH: 39.16 LN.M., BRIDGE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

31 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

SIPAG - FLOOD MITIGATION STRUCTURES - PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF WATER TREATMENT PLANT FACILITY WITH FLOODGATE & PUMPING STATION, CATCHMENT 1 (PHASE 3), ZAMBOANGA CITY

Region IX, Region IX

2024₱144.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF DETENTION TANK 2, WATER TREATMENT PLANT FACILITIES WITH FLOODGATE AND PUMPING STATION 2 ZAMBOANGA CITY

Region IX, Region IX

2022₱144.6M
Past target date (DPWH On-Going)
No sat.

WIDENING OF PERMANENT BRIDGES - TIGBAO BRIDGE (B00556MN) ALONG PAGADIAN CITY - ZAMBOANGA CITY ROAD, LICOMO, ZAMBOANGA CITY

Region IX, Region IX

2019₱116.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF DETENTION TANK 2, WATER TREATMENT PLANT FACILITIES WITH FLOODGATE AND PUMPING STATION 2, ZAMBOANGA CITY, CATCHMENT 1 (PHASE II)

Region IX, Region IX

2023₱115.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF PULIRAN BRIDGE ALONG ZAMBOANGA COASTAL ROAD, ZAMBOANGA DEL NORTE, STA. 2011+300.00 - STA. 2011+800.00; ABUTMENT -A : STA. 2011+532.08; ABUTMENT -B : STA. 2011+652.92 (APPROACHES NET LENGTH : 379.16 LN.M.) (BRIDGE LENGTH: 120.84 LN.M.)

Region IX, Region IX

2016₱112.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ACCESS ROAD AT SITIO ANULING, PAMUCUTAN TO STA. RITA IN SUPPORT OF HIGH VALUE CROPS (ABACA, CACAO, RUBBER AND COFFEE), UPPER LA PAZ, ZAMBOANGA CITY, PACKAGE III

Region IX, Region IX

2021₱111.3M
Reported complete (100% progress, DPWH status On-Going)
View all 31 projects →

4. Implementation

Contract Amount

₱107,551,634.49

Progress

Past target date (DPWH On-Going)

Start Date

June 15, 2017

Target End

June 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IX (Zamboanga Peninsula)City of ZamboangaManicahan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.