Bridges23DL0080

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 10. CONSTRUCTION OF MANGGALAYAN LABAK BRID

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 10. CONSTRUCTION OF MANGGALAYAN LABAK BRID is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱15,190,000.00. Status: Reported complete (DPWH). Contractor on record: F F ROSALES GEN CONTRACTOR. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure along Pipisik River, Gumaca, Quezon, Package A
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Quezon 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱15,190,000.00

Progress

Reported complete (DPWH)

Start Date

March 23, 2023

Target End

November 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.