GAA 2023 OO-123GB0091

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, CLUSTER 2- ARAS-ASAN BR (B00426PN) ALONG ANINI-Y T

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, CLUSTER 2- ARAS-ASAN BR (B00426PN) ALONG ANINI-Y T is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱137,102,061.90. Status: Past target date (DPWH On-Going). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Binangbang River, Barangay Poblacion, Barbaza, Antique
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Antique DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

299 projects · ₱22.3B total · 0 flags

4. Implementation

Contract Amount

₱137,102,061.90

Progress

Past target date (DPWH On-Going)

Start Date

May 8, 2023

Target End

July 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.