GAA 2025 SSP25IB0082

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GAP-ANG, DOLORES, EASTERN SAMAR

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GAP-ANG, DOLORES, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱4,886,648.47. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SAN-ANTONIO DE PADUA CONST. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱20,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25IB0082 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-07-17 → 2015-07-17

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GAP-ANG, DOLORES, EASTERN SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Guibuangan, Can-Avid, Eastern Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Eastern Samar DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,886,648.47

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 3, 2025

Target End

November 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GAP-ANG, DOLORES, EASTERN SAMAR.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/fc900ca9-f089-4418-b55e-ed0eb6cc5055

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)Eastern SamarDoloresGap-ang
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.