Roads23E00051

ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS, PTO. PRINCESA NORTH ROAD, K0150+030-K0150+140, PALAWAN

ASSET PRESERVATION PROGRAM- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS, PTO. PRINCESA NORTH ROAD, K0150+030-K0150+140, PALAWAN is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱117,155,917.36. Status: Past target date (DPWH On-Going). Contractor on record: BALINTUGAN CONST. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

92 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROADKO228+067 - KO228+170KO229+090 - KO229+2

Cordillera Administrative Region, Cordillera Administrative Region

2020₱243.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B)

Cordillera Administrative Region, Cordillera Administrative Region

2020₱234.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF LENGTAN FLOOD CONTROL ALONG CHICO RIVER, SAMOKI, BONTOC, MOUNTAIN PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENNON ROAD - K0223 + 749 - K0223 + 890TUBA, BEN

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BAGUIO - BONTOC ROADKO302+180 - KO302+300, KO314+

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO234+910 - KO235+020, KO238+870 - KO238

Cordillera Administrative Region, Cordillera Administrative Region

2021₱173.7M
Reported complete (DPWH)
View all 92 projects →

4. Implementation

Contract Amount

₱117,155,917.36

Progress

Past target date (DPWH On-Going)

Start Date

April 5, 2023

Target End

January 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.