CLUSTER 41-FLOOD CONTROL AND DRAINAGE PROTECTION WORKS DAMAGED BY TYPHOON NINA: REHAB/ RESTORATION OF COMON LINE CANAL, TABACO CITY AND SAN ISIDRO PIPE CULVERT INTO BOX CULVERT, TABACO CITY
CLUSTER 41-FLOOD CONTROL AND DRAINAGE PROTECTION WORKS DAMAGED BY TYPHOON NINA: REHAB/RESTORATION OF COMON LINE CANAL, TABACO CITY AND SAN ISIDRO PIPE CULVERT INTO BOX CULVERT, TABACO CITY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱9,279,536.50. Status: Reported complete (DPWH). Contractor on record: WATERTON CONST. Figures trace to dpwh.
DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.
No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.
Total Contract Cost