Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 22, 2026

High Concurrent Workload for One Contractor

Contractor linked to many simultaneous projects or very high total value vs peers.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: A C SOLIVEN CONST & GEN MERCHANDISE holds 40 flood-control contracts worth ₱2.09B, 2.06× the 95th-percentile contractor total (₱1.01B); up to 20 ran at the same time. This is a capacity question worth examining. The contractor may have unusually high capacity or specialization in flood-control projects.

Public record entityA C SOLIVEN CONST & GEN MERCHANDISEOrganization record →
Location—
AmountData not yet available sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 40Ongoing: 0Delayed: 0Status unknown: 0
Show 34 more projects in this bucket
Construction of Flood Control Structure along Meycauayan River, Sta. 01+950 - Sta. 02+100 (Liputan - Ubihan Section), Meycauayan, Bulacan24CD0001Flood control100%January 8, 2025January 8, 2025—completedsumbong source
Construction of Flood Control Structure along Rio Chico River (Segment S), Victoria, Tarlac24CJ0018Flood control100%July 19, 2024June 21, 2024—completedsumbong source
Construction of Flood Control Structure along Tarlac River - O'Donnell River Control, Balanti-Armenia Section (Segment N), Tarlac City, Tarlac24CJ0032Flood control100%July 19, 2024July 19, 2024—completedsumbong source
Construction of Flood Control Structure along Ungot Creek (Segment S), Tarlac City, Tarlac24CJ0051Flood control100%July 19, 2024May 18, 2024—completedsumbong source
Construction of Flood Mitigation Structure along Tarlac River Control, Left Dike, Tibagan-Tibag Section (Package F), Tarlac City22CJ0028Flood control100%July 15, 2022July 15, 2022—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Camiling River Right Bank, Cacamilingan Sur-Cacamilingan Norte Section (Package A), Camiling, Tarlac23CJ0133Flood control100%July 29, 2023June 22, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Camiling River, Left Bank, Anoling 1st to Pao 1st Section (Package A), Camiling, Tarlac23CJ0008Flood control100%July 29, 2023June 15, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Camiling River, Left Bank, Anoling 1st to Pao 1st Section (Package B), Camiling, Tarlac23CJ0011Flood control100%July 29, 2023June 15, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Camiling River, Right Bank, Surgui 1st - Cacamilingan Sur Section (Package A), Camiling, Tarlac23CJ0134Flood control100%August 2, 2023June 21, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Camiling River, Right Bank, Telbang - Baybayaoas Section (Package B), Camiling, Tarlac23CJ0059Flood control100%July 29, 2023May 25, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Delinquente Creek, Bacabac Section (Package 1), Camiling, Tarlac23CJ0014Flood control100%July 29, 2023April 24, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along O'Donnell River Control Right Dike, Armenia-San Jose De Urquico Section (Package B), Tarlac City, Tarlac23CJ0042Flood control100%July 29, 2023July 29, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along O'Donnell-Tarlac River (Right Dike), Armenia-Aguso Section, Tarlac City, Tarlac23CJ0080Flood control100%December 10, 2023August 15, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Tarlac River Control Left Dike, Brillante-Rang-Ayan Section (Package G), Rang-Ayan, Paniqui, Tarlac23CJ0003Flood control100%July 29, 2023July 18, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation along Tarlac River Control Left Dike, San Jose-San Bartolome Section (Package C), Gerona, Tarlac23CJ0016Flood control100%July 29, 2023June 19, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation Along Tarlac River Control Right Dike, Colibangbang Section (Package H), Barangay Colibangbang, Paniqui, Tarlac23CJ0073Flood control100%November 16, 2023November 16, 2023—completedsumbong source
Rehabilitation of Existing Dike along Aranguren Creek, Left Bank, U/S of Calumpit Bridge, Capas, Tarlac23CK0038Flood control100%June 26, 2023June 13, 2023—completedsumbong source
Rehabilitation of Existing Dike along Lucung River (Jefmin Section, Left Bank), D/S of Santiago Bridge, Package 2, Concepcion, Tarlac23CK0040Flood control100%July 3, 2023July 3, 2023—completedsumbong source
Rehabilitation of Existing Dike along Lucung River (Old Lucung Lilibangan & Magao Section), Concepcion, Tarlac23CK0041Flood control100%July 4, 2023June 26, 2023—completedsumbong source
Rehabilitation of Existing Dike along Rio Chico River (Castillo Section, Right Bank), Phase 3, Sta. (-)1+737.60 - Sta. (-)1+926.25 Concepcion, Tarlac24CK0025Flood control100%June 30, 2024June 30, 2024—completedsumbong source
Rehabilitation of Existing Dike along Rio Chico River (Rizal-Balanoy Section, Right Bank) Package 1, La Paz, Tarlac23CK0045Flood control100%June 26, 2023May 9, 2023—completedsumbong source
Rehabilitation of Existing Dike along Rio Chico River, (Balanoy Section, Right Bank), Phase 2, Sta. (-) 5+594.31 to Sta. (-) 6+058.62, La Paz, Tarlac24CK0049Flood control100%August 21, 2024May 23, 2024—completedsumbong source
Rehabilitation of Flood Control Structure along Tarlac River Control (Right Dike), Tagumbao-Dicolor Section (Package B), Sta. 0+000 - Sta. 0+313, Gerona, Tarlac22CJ0014Flood control100%September 24, 2022July 18, 2022—completedsumbong source
Construction of Existing Dike along Lucung River, Cut-Cut II Section, Right Bank, Capas, Tarlac23CK0051100%September 16, 2023September 16, 2023—completedsumbong source
Construction of Flood Control Structure along Banila River, Brgy. Cabalitian, Umingan, Pangasinan22AI0094100%August 1, 2022February 21, 2023—completedsumbong source
Construction of Flood Control Structure along Mitura River, Brgy.Sobol - Brgy. Toboy, Asingan, Pangasinan23AI0082100%September 28, 2023September 28, 2023—completedsumbong source
Construction of Flood Control Structure along Totonoguen River, Brgy. Zone 5, Rosales, Pangasinan24AI0035100%August 8, 2024July 15, 2024—completedsumbong source
Construction of River Protection along Barangay Dampol II-B, Pulilan, Bulacan22CC0005100%July 26, 2022July 4, 2022—completedsumbong source
Construction of Slope Protection along Banila River, Balungao - Rosales, Pangasinan (Package 1)22AI0137100%October 25, 2022October 25, 2022—completedsumbong source
Construction of Slope Protection along Banila River, Balungao - Rosales, Pangasinan (Package 2)22AI0148100%October 25, 2022October 25, 2022—completedsumbong source
Construction of Slope Protection Structure along Camiling River, Poblacion D to G Serction (Package C), Camiling, Tarlac22CJ0194100%November 29, 2022November 29, 2022—completedsumbong source
Construction of Slope Protection Structure along Tarlac River (Left Dike), Brillante-Aduas (Package M), Paniqui, Tarlac24CJ0065100%October 5, 2024June 19, 2024—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation and Road Component along Camiling River Left Bank, Anoling 3rd to Pao 1st Section , Camiling, Tarlac (Package F)23CJ0139100%September 13, 2023September 13, 2023—completedsumbong source
Construction of Slope Protection with Steel Sheet Pile Foundation and Road Component Along Camiling River Left Bank, Anoling 3rd to Pao 1st Section, Camiling, Tarlac (Package G)23CJ0141100%September 13, 2023September 13, 2023—completedsumbong source

Rule Definition

Active project count and total value vs peer 95th percentile.

Triggering Data & citations

Contractor carries far more concurrent flood-control value than peers

{
  "contractor": "A C SOLIVEN CONST & GEN MERCHANDISE",
  "projectCount": 40,
  "totalValuePhp": 2089544591.02,
  "peerP95TotalPhp": 1014143494.4100002,
  "activeProjectCount": 0,
  "simultaneousThreshold": 25
}

Possible Innocent Explanations

  • Large national firm with many concurrent government clients
  • Data groups joint ventures under one name