Construction of Slope Protection Structure23CJ0141

Construction of Slope Protection with Steel Sheet Pile Foundation and Road Component Along Camiling River Left Bank, Anoling 3rd to Pao 1st Section, Camiling, Tarlac (Package G)

Construction of Slope Protection with Steel Sheet Pile Foundation and Road Component Along Camiling River Left Bank, Anoling 3rd to Pao 1st Section, Camiling, Tarlac (Package G) is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱48,050,158.90. Status: Reported complete (DPWH). Contractor on record: A C SOLIVEN CONST & GEN MERCHANDISE. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tarlac District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

40 projects · ₱2.1B total · 22 flags

4. Implementation

Contract Amount

₱48,050,158.90

Progress

Reported complete (DPWH)

Start Date

March 17, 2023

Target End

September 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.