Rehabilitation / Major Repair of Flood Control Structure24CK0025

Rehabilitation of Existing Dike along Rio Chico River (Castillo Section, Right Bank), Phase 3, Sta. (-)1+737.60 - Sta. (-)1+926.25 Concepcion, Tarlac

Rehabilitation of Existing Dike along Rio Chico River (Castillo Section, Right Bank), Phase 3, Sta. (-)1+737.60 - Sta. (-)1+926.25 Concepcion, Tarlac is a DPWH-tracked public work in CONCEPCION (TARLAC), TARLAC, Region III. Reported contract value: ₱46,750,558.17. Status: Reported complete (DPWH). Contractor on record: A C SOLIVEN CONST & GEN MERCHANDISE. Figures trace to sumbong.

CONCEPCION (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River Control ( Right Dike ) , Villa Paz - Dicolor Section, Gerona, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008260

₱1,425,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008262

₱132,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

40 projects · ₱2.1B total · 22 flags

4. Implementation

Contract Amount

₱46,750,558.17

Progress

Reported complete (DPWH)

Start Date

February 5, 2024

Target End

June 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.