Construction of Slope Protection with Steel Sheet Pile Foundation along Delinquente Creek, Bacabac Section (Package 1), Camiling, Tarlac is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱48,139,898.83. Status: Reported complete (DPWH). Contractor on record: A C SOLIVEN CONST & GEN MERCHANDISE. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-23-0027032

₱10,268,343.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,139,898.83

Progress

Reported complete (DPWH)

Start Date

January 30, 2023

Target End

July 29, 2023

5. Audit