Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 4 contracts awarded to CENTERWAYS CONST AND DEVELOPMENT INC by the same office started within 112 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is possible these are separate projects in different barangays as part of a coordinated flood control program.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Bito River Flood Mitigation Structure along Brgy. Corbada, San Fernando, Masbate23F00141Flood control | 100% | February 2, 2024 | February 2, 2024 | No target date from DPWH, so lateness cannot be computed | completedsumbong source |
Start: March 24, 2023 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Masbate 1st District Engineering Office",
"contractId": "23F00141",
"contractor": "CENTERWAYS CONST AND DEVELOPMENT INC",
"windowDays": 120,
"clusterSize": 4,
"thresholdPhp": 50000000,
"contractCostPhp": 48249363.78,
"averageTitleSimilarity": 0.9003818464637089
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program