Hon. JB Bernos Representative, Abra (Lone District) House of Representatives Subject: Request for explanation and documents on FY2027 DPWH budget lines for Abra (Lone District) Dear Representative JB Bernos: Good day. I live in Abra (Lone District), and I would like to ask about some DPWH lines for the Abra DEO in the FY2027 budget. When I compared the National Expenditure Program (NEP) with House Bill No. 10858 (third reading), I noticed the following: 1. Rehabilitation of Ababeng-Domeguiay Road, La Paz and Danglas, Abra (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 468; no matching NEP line for this office] 2. Rehabilitation of Canan-Lagayan Road to Baybayatin, La Paz and Lagayan, Abra, (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 468; no matching NEP line for this office] 3. Rehabilitation of Garreta-Laskig-San Diego Road, Pidigan, Abra (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 468; no matching NEP line for this office] 4. Rehabilitation of Poblacion-Pulot-Kiwas Road, Lagayan, Abra (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 468; no matching NEP line for this office] 5. Rehabilitation/Construction of Multi-Purpose Building, Poblacion, La Paz, Abra (17.67413, 120.684469) (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 682; no matching NEP line for this office] 6. Construction (Completion) of Multi-Purpose Building, Zone 5, Bangued, Abra 17.596246, 120.618253 (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 682; no matching NEP line for this office] 7. Construction of Multi Purpose Building, North Poblacion, La Paz, Abra (Abra DEO): not in the NEP; ₱50,000,000 in the House version. [HB 10858 (3rd Reading) Vol. I-C, p. 682; no matching NEP line for this office] For each line above, may I ask for: 1. The reason or basis for adding, increasing, reducing or removing it, and who requested it; 2. The feasibility study, program of work, or detailed engineering design, if one exists; 3. The exact location and the expected beneficiaries; and 4. Any earlier projects at the same location and their status. For context, this is what public DPWH records show for past projects: - Abra DEO: 1,752 contracts (2016–2025) in public DPWH records; 1,227 recorded as completed and 420 as ongoing. Some of these were marked by automated indicators on public data. These are not findings of wrongdoing; I would only like an explanation for: - Construction of Salangsang Flood Control Structure, La Paz, Abra (24PA0037): Awards Very Close to the Budget Ceiling. https://lovethephilippines.com/projects/6743af42-ff46-4b37-aca6-914d801057e5 - Construction of Flood Control Structure along Abra Major River Basin, Barangay San Jose Sur, Manabo, Abra (23PA0253): Awards Very Close to the Budget Ceiling. https://lovethephilippines.com/projects/ab6100b6-891c-4577-9a43-6d5caded9a7e - Construction of Quidaoen - Cabcaburao Flood Control Structure (Phase 2), Barangay Quidaoen to Barangay Cabcaborao, San Juan, Abra (22PA0045): Pattern Consistent with Contract Splitting; Awards Very Close to the Budget Ceiling. https://lovethephilippines.com/projects/72faa304-a02e-4fc9-8117-6f8c18aee29d - Construction of Pagala Flood Control Structure (Phase 2), Barangay Pagala, Bucay, Abra (22PA0103): Awards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting. https://lovethephilippines.com/projects/1e77e199-2ae9-42ae-bb9f-3b7a3aa62140 - Construction of Bangcagan Flood Control Structure, Barangay Bangcagan, Bucay, Abra (22PA0104): Awards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting; Cross-Source Mismatch (PhilGEPS vs DPWH). https://lovethephilippines.com/projects/fe83299a-eef8-463b-a2e7-a9a15008c039 I am asking only for information and am not alleging any wrongdoing. Thank you for your time and your reply. Respectfully, [Your name] [Barangay, city or municipality] — Sources: House Bill No. 10858, third reading, Vol. I-C (DPWH); National Expenditure Program FY2027, Vol. II-B (DBM). Data as of 2026-10-31. Page numbers are given on each line. Prepared with https://lovethephilippines.com/write-your-rep/abra-lone
Write your representative · FY2027 budget
Abra (Lone District)
Representative: JB Bernos · bills and roles · official House profile
Served by: Abra DEO. Committee memberships are not shown because the House has not published a machine-readable list.
Language / Wika
Tone
Lines to include
Sign it (stays in your browser; nothing is sent or saved)
We do not have a sourced email address for this office, so the email opens with the “To” field blank. Find the office’s contact details on the official House profile. Long letters are shortened in the email link; use Copy for the full text.
7 of 11 lines selected.
Letters for this district so far: 1 opened · 0 copied · 0 sent to email. Anonymous totals only; we store no names, emails or IP addresses.
Abra DEO
- House version (HB 10858)
- ₱835.3M
- 20 lines
- President’s NEP
- ₱685.3M
- 17 lines
- Added by the House
- 7
- ₱350.0M
- Changed / removed
- 0 / 4
- 13 lines unchanged
Lines that differ from the NEP (7)
| Line | Change | NEP | House | Sources |
|---|---|---|---|---|
| Rehabilitation of Ababeng-Domeguiay Road, La Paz and Danglas, Abra | Added by the House | — | ₱50,000,000 | HB p. 468 |
| Rehabilitation of Canan-Lagayan Road to Baybayatin, La Paz and Lagayan, Abra, | Added by the House | — | ₱50,000,000 | HB p. 468 |
| Rehabilitation of Garreta-Laskig-San Diego Road, Pidigan, Abra | Added by the House | — | ₱50,000,000 | HB p. 468 |
| Rehabilitation of Poblacion-Pulot-Kiwas Road, Lagayan, Abra | Added by the House | — | ₱50,000,000 | HB p. 468 |
| Rehabilitation/Construction of Multi-Purpose Building, Poblacion, La Paz, Abra (17.67413, 120.684469) | Added by the House | — | ₱50,000,000 | HB p. 682 |
| Construction (Completion) of Multi-Purpose Building, Zone 5, Bangued, Abra 17.596246, 120.618253 | Added by the House | — | ₱50,000,000 | HB p. 682 |
| Construction of Multi Purpose Building, North Poblacion, La Paz, Abra | Added by the House | — | ₱50,000,000 | HB p. 682 |
NEP lines with no match in the House version (4)
- Construction of Ababeng-Domeguiay Road, La Paz and Danglas, Abra · ₱50,000,000 · NEP PDF p. 469
- Construction of Canan-Lagayan Road leading to Baybayatin Indigenous People (IP) Community, La Paz and Lagayan, Abra, · ₱50,000,000 · NEP PDF p. 469
- Construction of Garreta-Laskig-San Diego Road, Pidigan, Abra · ₱50,000,000 · NEP PDF p. 469
- Construction of Poblacion-Pulot-Kiwas Road, Lagayan, Abra · ₱50,000,000 · NEP PDF p. 469
A line can look removed when the House reworded its title. Treat these as questions.
Past DPWH contracts under this office
1,752 contracts from 2016 to 2025 in public DPWH records (₱68.80B): 1,227 recorded as completed, 420 as ongoing. 1,633 have a satellite image check on file. Browse them.
75 past contracts marked by public-data indicators
Indicators are automated statistical checks on public data. They are not findings of wrongdoing, and a marked contract may have a full explanation.
- Construction of Salangsang Flood Control Structure, La Paz, Abra 24PA0037 · Completed · ₱148.5MAwards Very Close to the Budget Ceiling · satellite before / after
- Construction of Flood Control Structure along Abra Major River Basin, Barangay San Jose Sur, Manabo, Abra 23PA0253 · Completed · ₱144.8MAwards Very Close to the Budget Ceiling · satellite before / after
- Construction of Quidaoen - Cabcaburao Flood Control Structure (Phase 2), Barangay Quidaoen to Barangay Cabcaborao, San Juan, Abra 22PA0045 · Completed · ₱49.5MPattern Consistent with Contract Splitting; Awards Very Close to the Budget Ceiling
- Construction of Pagala Flood Control Structure (Phase 2), Barangay Pagala, Bucay, Abra 22PA0103 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting
- Construction of Bangcagan Flood Control Structure, Barangay Bangcagan, Bucay, Abra 22PA0104 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting; Cross-Source Mismatch (PhilGEPS vs DPWH)
- Construction of Pulot Flood Control Structure (Phase 2), Barangay Pulot, Lagayan, Abra 22PA0053 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling
- Construction of Salip Flood Control, Barangay Poblacion, La Paz, Abra 22PA0079 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting
- Construction of Sabangan Flood Control, Buli, La Paz, Abra 22PA0084 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting
- Construction of Patagui Flood Control, Poblacion, La Paz, Abra 22PA0085 · Completed · ₱49.5MPattern Consistent with Contract Splitting; Awards Very Close to the Budget Ceiling
- Construction of Poblacion Flood Control Structure (Phase 2), Barangay Poblacion, La Paz, Abra 22PA0088 · Completed · ₱49.5MPattern Consistent with Contract Splitting; Awards Very Close to the Budget Ceiling
- Construction of Poblacion Flood Control Structure (Phase 3), Barangay Poblacion, La Paz, Abra 22PA0089 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting
- Construction of Soot Flood Control Structure (Phase 2), Barangay Mudeng, La Paz, Abra 22PA0090 · Completed · ₱49.5MAwards Very Close to the Budget Ceiling; Pattern Consistent with Contract Splitting
How this was made. House lines come from the native text of House Bill No. 10858, third reading, Vol. I-C (official record); every one of the 15,977 amounts was checked against its printed page. NEP lines come from the FY2027 National Expenditure Program, Vol. II-B as read by the open BetterGov DPWH NEP–HB analysis. Lines are matched by office and title. A line marked “added” had no matching title under the same office in the NEP; “uncertain” means a similar title appears in the DPWH Transparency NEP listing or our own NEP reading, or the scan reading of the NEP amount needs a check. Past contracts and indicators come from public DPWH records on this site.
Disclaimer. This page and the letters it makes ask for explanations and documents. They do not say that anyone did anything wrong. A budget change can have a good reason; that is what the letter asks about. Your name and place stay in your browser and are never sent to us.