6 published flags on records linked to Makinabang and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C7 · High Concurrent Workload for One ContractorL R Tiqui Builders IncContractor (applies to all its work) · contractor L R Tiqui Builders Inc
- C7 · High Concurrent Workload for One ContractorTopnotch Catalyst Builders IncContractor (applies to all its work) · contractor Topnotch Catalyst Builders Inc
- C7 · High Concurrent Workload for One ContractorM3 Konstract Corp Formerly:Margarita ConstContractor (applies to all its work) · contractor M3 Konstract Corp Formerly:Margarita Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Major River System, Angat River, Culianin and Makinabang Section, Sta. 00 + 632 to Sta. 01 + 007, Plaridel/Baliwag, BulacanDPWH project · contractor A R L Const
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Angat River, Makinabang Section, Sta. 0 + 000 to Sta. 0 + 353.60, Baliuag, BulacanDPWH project · contractor Topnotch Catalyst Builders Inc
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure at Barangay Tangos, Baliuag, Bulacan (K003+200 to K003+500)DPWH project · contractor Ypr Gen Contractor and Const Supply Inc