Buildings and Facilities18H00065

CONSTRUCTION OF THE DEPARTMENT OF AGRICULTURE REGION 7 (DA-7) BUILDING, GUADALUPE, CEBU CITY

CONSTRUCTION OF THE DEPARTMENT OF AGRICULTURE REGION 7 (DA-7) BUILDING, GUADALUPE, CEBU CITY is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱79,589,994.75. Status: Reported complete (DPWH). Contractor on record: ML_BUILDERS INC. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

15 projects · ₱1.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF NRJ TAGBALILI-DUMAGANAS ROAD PHASE 2, ESPERANZA, AGUSAN DEL SUR

Region XIII, Region XIII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, NRJ BUTUAN CITY MALAYBALAY ROAD TUNGAO (BUTUAN CITY), LEADING TO SITIO DANAPA TO NRU LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPI, CARMEN (LASBUENASCAR) BARANGAY DURIAN, LAS NIEVES, AGUSA

Region XIII, Region XIII

2025₱192.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, NRJ BUTUAN CITY MALAYBALAY ROAD TUNGAO (BUTUAN CITY), LEADING TO SITIO DANAPA TO NRJ LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPIT, CARMEN (LASBUENASCAR), BARANGAY DURIAN, LAS NIEVES,

Region XIII, Region XIII

2023₱144.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KAWAYAN RIVER, TACLOBAN CITY

Tacloban City DEO, Region VIII

2024₱144.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP) - CONSTRUCTION OF ROAD LEADING TO TANAP AVIS FALLS, BURGOS, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2024₱92.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS- CEBU BALAMBAN TRANSCENTRAL HIGHWAY -K0020+493-K0020+679, CEBU CITY

Cebu City DEO, Region VII

2023₱67.4M
Reported complete (DPWH)
View all 15 projects →

4. Implementation

Contract Amount

₱79,589,994.75

Progress

Reported complete (DPWH)

Start Date

December 28, 2018

Target End

May 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.