Flood Control and Drainage24IM0010

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KAWAYAN RIVER, TACLOBAN CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KAWAYAN RIVER, TACLOBAN CITY is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱144,692,254.52. Status: Past target date (DPWH On-Going). Contractor on record: ML_BUILDERS INC. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Drainage ) , barangay 62 - B, Tacloban City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Tacloban City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

15 projects · ₱1.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF NRJ TAGBALILI-DUMAGANAS ROAD PHASE 2, ESPERANZA, AGUSAN DEL SUR

Region XIII, Region XIII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, NRJ BUTUAN CITY MALAYBALAY ROAD TUNGAO (BUTUAN CITY), LEADING TO SITIO DANAPA TO NRU LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPI, CARMEN (LASBUENASCAR) BARANGAY DURIAN, LAS NIEVES, AGUSA

Region XIII, Region XIII

2025₱192.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, NRJ BUTUAN CITY MALAYBALAY ROAD TUNGAO (BUTUAN CITY), LEADING TO SITIO DANAPA TO NRJ LINGAYAO-INTERIM BARANGAY OF LAWAN-LAWAN ROAD IN SUPPORT OF LAS NIEVES, BUENAVISTA, NASIPIT, CARMEN (LASBUENASCAR), BARANGAY DURIAN, LAS NIEVES,

Region XIII, Region XIII

2023₱144.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP) - CONSTRUCTION OF ROAD LEADING TO TANAP AVIS FALLS, BURGOS, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2024₱92.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF THE DEPARTMENT OF AGRICULTURE REGION 7 (DA-7) BUILDING, GUADALUPE, CEBU CITY

Region VII, Region VII

2018₱79.6M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS- CEBU BALAMBAN TRANSCENTRAL HIGHWAY -K0020+493-K0020+679, CEBU CITY

Cebu City DEO, Region VII

2023₱67.4M
Reported complete (DPWH)
View all 15 projects →

4. Implementation

Contract Amount

₱144,692,254.52

Progress

Past target date (DPWH On-Going)

Start Date

February 22, 2024

Target End

January 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.