Buildings and Facilities21CF0190

CONSTRUCTION/IMPROVEMENT/ENHANCEMENT OF HHQ S BATTERY HAAR-PHILIPPINE ARMY, FORT MAGSAYSAY, NUEVA ECIJA

CONSTRUCTION/IMPROVEMENT/ENHANCEMENT OF HHQ S BATTERY HAAR-PHILIPPINE ARMY, FORT MAGSAYSAY, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱19,401,855.32. Status: Reported complete (DPWH). Contractor on record: JERRY R SANTIAGO CONST CORP FORMERLY: JERRY SANTIAGO CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIVA-21-0008181 · ₱737,790,000 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21CF0190 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-03-19 → 2020-03-19

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/IMPROVEMENT/ENHANCEMENT OF HHQ S BATTERY HAAR-PHILIPPINE ARMY, FORT MAGSAYSAY, NUEVA ECIJA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Julo, Municipality of San Antonio, Nueva Ecija
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱737,790,000.00 · FY2021

Released to Laguna 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

58 projects · ₱1.6B total · 1 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT/REHABILITATION/COMPLETION OF VARIOUS MULTI-PURPOSE BUILDINGS (COVERED COURT, BRGY. HALL, EVACUATION CENTER), CALAPAN CITY, ORIENTAL MINDORO

Mindoro Oriental DEO, Region IV-B

2022₱131.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - STA. ROSA - TARLAC RD - K0108 + (-881) - K0108 + (-803), K0111 + 100 - K0111 + 832, K0112 + 576.50 - K0113 + 082, K0116 + 000 - K0117 + 724

Nueva Ecija 2nd DEO, Region III

2024₱89.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS NUEVA ECIJA - AURORA RD. - K0131+007-K0131+843, K0132+066-K0133+000, K0133+233-K0134+500, K0135+835-K0136+461, K0137+900-K0138+144, K0139+2

Nueva Ecija 2nd DEO, Region III

2023₱86.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - NUEVA ECIJA - AURORA RD - K0129+543-K0129+743, K0129+743-K0129+995, K0130+000-K0131+000, K0131+700-K0131+997.50, K0132+000-K0132+11

Nueva Ecija 2nd DEO, Region III

2024₱86.6M
Reported complete (100% progress, DPWH status On-Going)

Construction of Flood Mitigation Structure along Pampanga River, Barangay Sapang Buho, Palayan City, Nueva Ecija

PALAYAN CITY (CAPITAL) (NUEVA ECIJA), NUEVA ECIJA, Region III

2024₱85.1M
Reported complete (DPWH)

Rehabilitation of Digmala River Control, Brgy. Tugatog, Bongabon, Nueva Ecija

BONGABON (NUEVA ECIJA), NUEVA ECIJA, Region III

2022₱82.0M
Reported complete (DPWH)
View all 58 projects →

4. Implementation

Contract Amount

₱19,401,855.32

Progress

Reported complete (DPWH)

Start Date

September 20, 2021

Target End

April 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “CONSTRUCTION/IMPROVEMENT/ENHANCEMENT OF HHQ S BATTERY HAAR-PHILIPPINE ARMY, FORT MAGSAYSAY, NUEVA ECIJA.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/051ee109-8da5-4ba1-8431-7508d080051b

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)Nueva EcijaCity of PalayanBo. Militar
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →