Roads23BJ0024

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE (TERTIARY ROAD) JCT. NATL ROAD-BITNONG-BELANCE-NUEVA VIZCAYA BDRY ROAD (K0262+138-K0262+240), DUPAX DEL NORTE, NUEVA VIZCAYA

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE (TERTIARY ROAD) JCT. NATL ROAD-BITNONG-BELANCE-NUEVA VIZCAYA BDRY ROAD (K0262+138-K0262+240), DUPAX DEL NORTE, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱58,777,300.00. Status: Reported complete (DPWH). Contractor on record: M R VARGAS CONST CORP FORMERLY: M R VARGAS CONST. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Apean River, Mabasa Section, Dupax del Norte, Nueva Vizcaya
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-23-002567

₱3,187,157.00 · FY2023

Released to 0300017 Regional Office IV - - - B (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

58 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱58,777,300.00

Progress

Reported complete (DPWH)

Start Date

April 4, 2023

Target End

August 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.