Construction of Flood Mitigation Structure23BI0005

Construction of Macate Flood Control Structure along Magat River, Bambang, Nueva Vizcaya

Construction of Macate Flood Control Structure along Magat River, Bambang, Nueva Vizcaya is a DPWH-tracked public work in BAMBANG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II. Reported contract value: ₱59,400,000.00. Status: Reported complete (DPWH). Contractor on record: M R VARGAS CONST CORP FORMERLY: M R VARGAS CONST. Figures trace to sumbong.

BAMBANG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sto. Domingo Flood Control Structure along Magat River, Bambang, Nueva Vizcaya
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Nueva Vizcaya District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

58 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING OF MOGPOG-BALANACA ROAD, K0013+650-K0015+871.00

Marinduque DEO, Region IV-B

2018₱96.5M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MANGA RIVER, BARANGAY MUNGUIA, DUPAX DEL NORT

Nueva Vizcaya 2nd DEO, Region II

2025₱71.6M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN LEONARDO CUPAS ALONG SANTA CRUZ RIVER, PHASE 1, BARANGAY SAN LEONARDO, BAMBANG, NUE

Nueva Vizcaya DEO, Region II

2025₱67.5M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING OF POTOTAN - TINA - LAMBUNAO RD - K0037 + 375 - K0041 + 000

Iloilo 2nd DEO, Region VI

2023₱64.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE (TERTIARY ROAD) JCT. NATL ROAD-BITNONG-BELANCE-NUEVA VIZCAYA BDRY ROAD (K0262+138-K0262+240), DUPAX DEL NORTE, NUEVA VIZCAYA

Nueva Vizcaya 2nd DEO, Region II

2023₱58.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (CONCRETING) OF ROAD AT BARANGAY ANGILAN TO BARANGAY BA

Bohol 3rd DEO, Region VII

2023₱49.1M
Reported complete (DPWH)
View all 58 projects →

4. Implementation

Contract Amount

₱59,400,000.00

Progress

Reported complete (DPWH)

Start Date

February 14, 2023

Target End

October 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.