Roads23KL0051

CONSTRUCTION OF ROAD FROM BRGY. PANGAYAWAN, GITAGUM TO BRGY. LAPAD, LAGUINDINGAN, MISAMIS ORIENTAL

CONSTRUCTION OF ROAD FROM BRGY. PANGAYAWAN, GITAGUM TO BRGY. LAPAD, LAGUINDINGAN, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱19,800,000.00. Status: Reported complete (DPWH). Contractor on record: VICTORIANO C LIM CONST CORP FORMERLY: VICTORIANO C LIM CONST. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱5,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-23-0026225 · ₱822,712 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23KL0051 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-12-12 → 2025-10-15

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD FROM BRGY. PANGAYAWAN, GITAGUM TO BRGY. LAPAD, LAGUINDINGAN, MISAMIS ORIENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, Lugait, Misamis Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0026225

₱822,712.00 · FY2023

Released to 0000000 Davao del Sur State - College (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,800,000.00

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

August 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)Misamis OrientalGitagumUlab
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.