Bridges16Z00009

BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON CONTRACT PACKAGE 1B

BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) I, DESIGN AND BUILD BRIDGES IN LUZON CONTRACT PACKAGE 1B is a DPWH-tracked public work in Bridges Management Cluster, Central Office. Reported contract value: ₱690,413,838.91. Status: Reported complete (DPWH). Contractor on record: R D INTERIOR JUNIOR CONST. Figures trace to dpwh.

Bridges Management Cluster, Central Office
Region: Central Office

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱690,413,838.91

Progress

Reported complete (DPWH)

Start Date

May 8, 2018

Target End

February 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.