Buildings and Facilities24HM0062

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF TWO (2) STOREY MULTI-PURPOSE BUILDING IN BARANGAY CALUNASAN, MARIA, SIQUIJOR

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF TWO (2) STOREY MULTI-PURPOSE BUILDING IN BARANGAY CALUNASAN, MARIA, SIQUIJOR is a DPWH-tracked public work in Siquijor DEO, Negros Island Region. Reported contract value: ₱1,939,614.13. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: QUICKSILVER CONST SERVICES. Figures trace to dpwh.

Siquijor DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cantaroc - A, Maria, Siquijor
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-24-0006016

₱39,000.00 · FY2024

Released to Barayong National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

60 projects · ₱193.9M total · 0 flags

Other projects by this contractor

View all 60 projects →

4. Implementation

Contract Amount

₱1,939,614.13

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 13, 2024

Target End

June 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.