Flood Control and Drainage25AA0076

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL STRUCTURE, BARANGAY NO. 62-B, NAVOTAS SOUTH, LAOAG CITY, ILOCOS NORTE

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL STRUCTURE, BARANGAY NO. 62-B, NAVOTAS SOUTH, LAOAG CITY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱4,748,638.07. Status: Past target date (DPWH On-Going). Contractor on record: UY CONDEV CORP FORMERLY:UY CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay No. 62-A, Navotas North, Laoag City, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-25-0008479

₱38,977,790.00 · FY2025

Released to Ilocos Norte 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

178 projects · ₱8.2B total · 0 flags

Other projects by this contractor

No sat.

IMPROVEMENT/ WIDENING OF NATIONAL ROADS ALONG BACOLOD SOUTH ROAD INCLUDING RROW (S00127NR), K0046+(-910) - K0048+533; K0059+781 - K0060+307.50; K0065+448 - K0071+696.60 , HINIGARAN AND BINALBAGAN, NEGROS OCCIDENTAL

Negros Occidental 2nd DEO, Negros Island Region

2017₱236.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD - BAYAWAN - KABANKALAN ROAD, INCL. RROW, NEGROS ORIENTAL, BAYAWAN, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2017₱215.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD - HIMAMAYLAN CITY - NEGROS ORIENTAL BOUNDARY - TAYASAN ROAD , NEGROS OCCIDENTAL

Region VI, Region VI

2018₱172.3M
Reported complete (DPWH)
No sat.

CSSP, SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, REHAB./RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG DUMAGUETE NORTH RD (DUMAGUETE-JCT BAIS-KABANKALAN)-K0006+100-K0006+1017, K0006+1078-K0009+330, K0009+460-K0010+395,

Region VII, Region VII

2024₱154.8M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF REVETMENT STRUCTURE ALONG OCOY RIVER, BRGY. CALABNUGAN, SIBULAN, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2025₱146.3M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT/ WIDENING OF KABANKALAN - BAIS ROAD (S00240NR), K0093+218 - K0098+483, KABANKALAN, NEGROS OCCIDENTAL

Negros Occidental 3rd DEO, Negros Island Region

2017₱140.9M
Reported complete (DPWH)
View all 178 projects →

4. Implementation

Contract Amount

₱4,748,638.07

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

June 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.