Flood Control and Drainage18NI0018

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CANAL W/ BOX CULVERT) TIGBAWAN, SAN ROQUE, LINGIG, SURIGAO DEL SUR

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CANAL W/ BOX CULVERT) TIGBAWAN, SAN ROQUE, LINGIG, SURIGAO DEL SUR is a DPWH-tracked public work in Surigao del Sur 2nd DEO, Region XIII. Reported contract value: ₱7,874,377.08. Status: Reported complete (DPWH). Contractor on record: ROWIE'S CONST. Figures trace to dpwh.

Surigao del Sur 2nd DEO, Region XIII
Region: Region XIII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱8,500

    Probable match · score 0.96

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-18-0009517 · ₱5,000,000 · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18NI0018 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-06-17 → 2025-11-27

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Davao Oriental

Based on the coordinates published with the DPWH record and NOAH file DavaoOriental.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL STRUCTURE (CANAL W/ BOX CULVERT) TIGBAWAN, SAN ROQUE, LINGIG, SURIGAO DEL SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱8,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Canal w/Box Culvert) Tigbawan, San Roque, Lingig, Surigao Del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0009517

₱5,000,000.00 · FY2018

Released to Surigao del Sur 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

139 projects · ₱2.0B total · 0 flags

4. Implementation

Contract Amount

₱7,874,377.08

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

July 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region XI (Davao Region)Davao OrientalBostonCawayanan
Storms whose wind field reached it
Koto 2025Jelawat 2023
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.