Roads19HE0017

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - BARANGAY SIMALA-LINDOGON ROAD LEADING TO SIMALA PARISH CHURCH, BRGY. SIMALA, SIBONGA, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - BARANGAY SIMALA-LINDOGON ROAD LEADING TO SIMALA PARISH CHURCH, BRGY. SIMALA, SIBONGA, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: HELM CONST. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-19-0017947

₱170,249.00 · FY2019

Released to Pampanga 1st District Engineering Offi Division of Koronadal City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

47 projects · ₱899.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTU

Cebu 3rd DEO, Region VII

2025₱95.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY BASAK SAN NICOLAS, CEBU CITY

Cebu City DEO, Region VII

2023₱86.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUBANGDAKU RIVER, CEBU CITY

Region VII, Region VII

2024₱67.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - SUBANGDAKU BR. (B00476CB) ALONG CEBU NORTH RD, CEBU CITY, CEBU

Cebu City DEO, Region VII

2025₱60.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, LUYANG - POO - LAZI ROAD - K0022+840 - K0023+000, LAZI, SIQUIJOR

Siquijor DEO, Negros Island Region

2023₱49.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GUADALUPE RIVER, BAR

Cebu City DEO, Region VII

2024₱48.9M
Reported complete (100% progress, DPWH status On-Going)
View all 47 projects →

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

September 26, 2019

5. Audit