Roads24GA0191

INSTALLATION OF SOLAR STREETLIGHTS ALONG AKLAN EAST ROAD K0290+224 K0294+144, K0302+631 K0309+747

INSTALLATION OF SOLAR STREETLIGHTS ALONG AKLAN EAST ROAD K0290+224 K0294+144, K0302+631 K0309+747 is a DPWH-tracked public work in Aklan DEO, Region VI. Reported contract value: ₱96,499,883.55. Status: Reported complete (DPWH). Contractor on record: SUPREME ABF CONST. Figures trace to dpwh.

Aklan DEO, Region VI
Region: Region VI

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-F-24-0017851 · ₱12,668,787 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24GA0191 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-07-25 → 2025-07-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: INSTALLATION OF SOLAR STREETLIGHTS ALONG AKLAN EAST ROAD  K0290+224  K0294+144, K0302+631 K0309+747

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aklan River, Kalibo, Aklan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-F-24-0017851

₱12,668,787.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

449 projects · ₱16.9B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 20: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-REHAB. OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG ITABIAK-SAN VICENTE ROAD, SAN VICENTE, PALAWAN, 20.1: STA. 167+325-STA. 167+445; 20.2: STA. 169+254-STA. 169+405; 20.3:

Region IV-B, Region IV-B

2022₱257.1M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION TO VILLAFLOR SECTION, LEFT SI

Region VII, Region VII

2024₱241.2M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MGMT. PROG., CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF LOBOC RIVER CONTROL STRUCTURE, TAMBANGAN SECTION (RIGHT SIDE), LOAY, BOHOL

Region VII, Region VII

2023₱236.3M
Past target date (DPWH On-Going)
No sat.

CLUSTER 17: SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG)-REHABILITATION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG TDC-PAGDANAN ROAD, 17.1: STA. 9+012-STA. 9+149; 17.2: STA. 7+893-STA. 7+946; 17.3: STA. 8+030-STA. 8+063; 17.4: STA. 7+94

Region IV-B, Region IV-B

2022₱216.3M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONSTN/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LOBOC RIVER CONTROL STRUCTURE, UGPONG SECTION, LOBOC, BOHOL

Region VII, Region VII

2023₱214.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-REHABILITATION OF ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG ITABIAK-SAN VICENTE ROAD, STA. 165+662-STA. 165+924, PALAWAN

Region IV-B, Region IV-B

2022₱193.0M
Reported complete (DPWH)
View all 449 projects →

4. Implementation

Contract Amount

₱96,499,883.55

Progress

Reported complete (DPWH)

Start Date

March 25, 2024

Target End

January 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)AklanBaleteFeliciano
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.