Buildings and Facilities17DQ0112

CONSTRUCTION OF THREE (3) STOREY NINE (9) CLASSROOM SCHOOL BUILDING AT BACOOR NHS GEORGETOWN, BACOOR CITY CAVITE

CONSTRUCTION OF THREE (3) STOREY NINE (9) CLASSROOM SCHOOL BUILDING AT BACOOR NHS GEORGETOWN, BACOOR CITY CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱24,007,072.72. Status: Reported complete (DPWH). Contractor on record: D. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures and other improvements, including removal of informal settlers along Zapote River Barangay Molino 7, Bacoor City, Cavite
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Cavite 3rd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

11 projects · ₱171.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOLBUILDING AT BAYANAN ELEMENTARY SCHOOL, BACOOR, CAVITE

Cavite 3rd DEO, Region IV-A

2017₱30.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS ALONG

Cavite 3rd DEO, Region IV-A

2021₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FOUR (4) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDINGAT GOV P. F. ESPIRITU ELEMENTARY SCHOOL, BACOOR, CAVITE

Cavite 3rd DEO, Region IV-A

2017₱21.3M
Reported complete (DPWH)
No sat.

PROPOSED CONSTRUCTION OF (4) STOREY (8) CLASSROOM AT REAL ELEMENTARY SCHOOL, BACOOR, CAVITE

Cavite 3rd DEO, Region IV-A

2017₱21.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE ALONG CAVITE-

Cavite 3rd DEO, Region IV-A

2021₱11.8M
Reported complete (DPWH)
No sat.

CLUSTER 2019LIP-02: CONSTRUCITON OF VARIOUS CONCRETE ROADS: A) CONCT. OF RD LEADING TO TALABAAN ELEM SCHOOL PROPER, BRGY. TALABAAN, MAMBURAO, B) CONCT OF RD BRGY. 4, MAMBURAO, C) CONCT. OF RD BRGY.7, MAMBURAO, D) CONCT. OF RD, SITIO MAASIM, BRGY.9, MAMBUR

Mindoro Occidental DEO, Region IV-B

2019₱9.5M
Reported complete (DPWH)
View all 11 projects →

4. Implementation

Contract Amount

₱24,007,072.72

Progress

Reported complete (DPWH)

Start Date

November 29, 2017

Target End

July 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.