Bridges25AF0017

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF COASTAL ACCESS ROAD FROM AGOO TO ARINGAY, LA UNION

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF COASTAL ACCESS ROAD FROM AGOO TO ARINGAY, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱96,495,699.93. Status: Past target date (DPWH On-Going). Contractor on record: ALCEL CONST. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Pideg, Tubao, La Union
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0006113

₱1,160,372.00 · FY2025

Released to Southern Philippines Agri-Business and Marine and Aquatic School of Technology (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

467 projects · ₱8.0B total · 10 flags

Other projects by this contractor

View all 467 projects →

4. Implementation

Contract Amount

₱96,495,699.93

Progress

Past target date (DPWH On-Going)

Start Date

February 25, 2025

Target End

October 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.