Construction of Slope Protection Structure23CH0030

Construction of Slope Protection along Balantacan River, Balantacan to Sta. Teresa 2nd , Lubao, Pampanga

Construction of Slope Protection along Balantacan River, Balantacan to Sta. Teresa 2nd , Lubao, Pampanga is a DPWH-tracked public work in LUBAO (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱39,193,042.59. Status: Reported complete (DPWH). Contractor on record: DMDANAN CONST AND TRADING. Figures trace to sumbong.

LUBAO (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Quitangil River, Sta. 8+750 - Sta. 10+658 (R/S), San Agustin, Magalang, Pampanga
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0019620

₱7,421,142.00 · FY2023

Released to Southern Philippines Agri-Business and Marine and Aquatic School of Technology (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

61 projects · ₱681.8M total · 2 flags

4. Implementation

Contract Amount

₱39,193,042.59

Progress

Reported complete (DPWH)

Start Date

March 20, 2023

Target End

August 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.