Roads23IB0021

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINANGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT TAFT-ORAS-SN POLICARPO-ARTECHE RD - K0901+040, K0926+810 - K0927+064, K0929+669 - K0932+111, K0944+864 - K0944+1034, K0958+959 -K0959+325

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINANGE ALONG NATIONAL ROADS - SECONDARY ROADS, JCT TAFT-ORAS-SN POLICARPO-ARTECHE RD - K0901+040, K0926+810 - K0927+064, K0929+669 - K0932+111, K0944+864 - K0944+1034, K0958+959 -K0959+325 is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱25,479,584.02. Status: Reported complete (DPWH). Contractor on record: TWO-BROTHERS CONST 45485. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, Hernani, Eastern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Eastern Samar DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱25,479,584.02

Progress

Reported complete (DPWH)

Start Date

February 16, 2023

Target End

August 13, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.