Construction of Revetment23E00008

Construction of Sta. Cruz Shore Protecion/Boulevard, Barangay Buyabod, Santa Cruz, Marinduque

Construction of Sta. Cruz Shore Protecion/Boulevard, Barangay Buyabod, Santa Cruz, Marinduque is a DPWH-tracked public work in SANTA CRUZ (MARINDUQUE), MARINDUQUE, Region IV-B. Reported contract value: ₱192,998,641.00. Status: Reported complete (DPWH). Contractor on record: HGG BUILDERS & SUPPLY. Figures trace to sumbong.

SANTA CRUZ (MARINDUQUE), MARINDUQUE, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Pag-asa, Santa Cruz, Marinduque
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-23-002534

₱12,248,151.00 · FY2023

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

41 projects · ₱5.5B total · 27 flags

4. Implementation

Contract Amount

₱192,998,641.00

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

August 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.