Bridges25D00028

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS GUINAYANGAN -TAGKAWAYAN DIVERSION ROAD, PACKAGE C, QUEZON

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS GUINAYANGAN -TAGKAWAYAN DIVERSION ROAD, PACKAGE C, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱140,384,953.94. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: M G LUALHATI CONST CORP. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱140,384,953.94

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

March 16, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.