Buildings and Facilities23PL0105

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZENS CENTER), TABUK CITY, KALINGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZENS CENTER), TABUK CITY, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱0.00. Status: Past target date (DPWH On-Going). Contractor on record: JBC BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, New Tanglag, Tabuk City, Kalinga
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-23-0025489

₱187,786,705.00 · FY2023

Released to Pangasinan State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

18 projects · ₱131.1M total · 0 flags

4. Implementation

Contract Amount

₱0.00

Progress

Past target date (DPWH On-Going)

Start Date

August 22, 2023

Target End

February 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.