Roads24HN0026

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD AT BRGY. MARIBAGO, LAPU-LAPU CITY, CEBU

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD AT BRGY. MARIBAGO, LAPU-LAPU CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱9,781,882.58. Status: Reported complete (DPWH). Contractor on record: GEETY REALTY AND DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Gate at Basak Creek, Lapu - Lapu City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,781,882.58

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

July 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.