Construction of Waterway22NC0049

Desilting of Solibao River (Phase I), Barangay Libuac & Barangay Poblacion, Rosario, Agusan del Sur

Desilting of Solibao River (Phase I), Barangay Libuac & Barangay Poblacion, Rosario, Agusan del Sur is a DPWH-tracked public work in ROSARIO (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII. Reported contract value: ₱96,499,999.50. Status: Reported complete (DPWH). Contractor on record: ARQ BUILDERS / MONOLITHIC CONST & CONCRETE PRODUCTS INC. Figures trace to sumbong.

ROSARIO (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Solibao River Flood Control, Rosario, Agusan Del Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0009075

₱2,023,257.00 · FY2022

Released to Luy-a National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003097

₱274,750,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-22-0004843

₱5,751,536.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-22-0004844

₱564,870.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-22-0004679

₱160,591.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱96.5M total · 0 flags

4. Implementation

Contract Amount

₱96,499,999.50

Progress

Reported complete (DPWH)

Start Date

October 19, 2022

Target End

August 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.