Buildings and Facilities18DJ0094

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM ACADEMIC SCHOOL BUILDING AT MORONG ELEMENTARY SCHOOL, SARIAYA, QUEZON

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM ACADEMIC SCHOOL BUILDING AT MORONG ELEMENTARY SCHOOL, SARIAYA, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱11,453,720.71. Status: Reported complete (DPWH). Contractor on record: SOUTHERN DAWN DEVELOPMENT CO 12294. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱11,453,720.71

Progress

Reported complete (DPWH)

Start Date

December 12, 2018

Target End

June 9, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.