Buildings and Facilities17DJ0070

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM ACADEMIC SCHOOL BUILDING AT CLARO M. RECTO MEMORIAL CENTRAL SCHOOL, TIAONG, QUEZON

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM ACADEMIC SCHOOL BUILDING AT CLARO M. RECTO MEMORIAL CENTRAL SCHOOL, TIAONG, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱10,646,691.65. Status: Reported complete (DPWH). Contractor on record: SOUTHERN DAWN DEVELOPMENT CO. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Aliliw, Lucban, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Quezon 2nd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱10,646,691.65

Progress

Reported complete (DPWH)

Start Date

November 24, 2017

Target End

May 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.