Roads24FN0019

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BAAO-IRIGA CITY-NABUA RD - K0470 + 580 - K0470 + 680

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BAAO-IRIGA CITY-NABUA RD - K0470 + 580 - K0470 + 680 is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱4,035,640.00. Status: Reported complete (DPWH). Contractor on record: EA-EC CONST AND SUPPLY. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Burabod Creek, Tigaon, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-24-0017484

₱1,551,485.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,035,640.00

Progress

Reported complete (DPWH)

Start Date

April 24, 2024

Target End

June 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.