GAA 2025 OO-125DN0119

BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - ANGONO BR. (B04739LZ) ALONG DIV RD ANGONO, RIZAL (FIRST DISTRICT)

BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - ANGONO BR. (B04739LZ) ALONG DIV RD ANGONO, RIZAL (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱47,776,010.38. Status: Past target date (DPWH On-Going). Contractor on record: F P DE GUZMAN CONST INC. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Angono River, Barangay San Vicente, Angono, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,776,010.38

Progress

Past target date (DPWH On-Going)

Start Date

July 10, 2025

Target End

December 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.