Roads24KM0044

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG OVERTON - BURU-UN BDRY RD - K1533+313 - K1533+380, K1534+840 - K1535+000

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG OVERTON - BURU-UN BDRY RD - K1533+313 - K1533+380, K1534+840 - K1535+000 is a DPWH-tracked public work in Iligan City DEO, Region X. Reported contract value: ₱49,000,000.00. Status: Past target date (DPWH On-Going). Contractor on record: KOUZBARY BUILDERS. Figures trace to dpwh.

Iligan City DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along LDNICR, Iligan City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Iligan City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

95 projects · ₱8.3B total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2024

Target End

April 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.