Construction of Slope Protection Structure21CJ0074

Construction of Road Slope Protection along Tarlac-Palauig Road, San Jose, Tarlac (Phase 4)

Construction of Road Slope Protection along Tarlac-Palauig Road, San Jose, Tarlac (Phase 4) is a DPWH-tracked public work in TARLAC, Region III. Reported contract value: ₱56,776,877.63. Status: Reported complete (DPWH). Contractor on record: R-II BUILDERS INC. Figures trace to sumbong.

TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱29,232,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Camiling River Right Bank, Telbang-Tuec Section (Phase III), Camiling, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005351

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008977

₱13,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013807

₱11,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014075

₱70,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000627

₱50,553.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000969

₱21,582.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000970

₱2,192.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000626

₱540,204.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

22 projects · ₱3.3B total · 0 flags

4. Implementation

Contract Amount

₱56,776,877.63

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

September 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.