Flood Control and Drainage19Z00006

CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER (SECTION A) AT GATTARAN, CAGAYAN

CONSTRUCTION OF BANK PROTECTION WORKS ALONG CAGAYAN RIVER (SECTION A) AT GATTARAN, CAGAYAN is a DPWH-tracked public work in Flood Control Management Cluster, Central Office. Reported contract value: ₱1,042,782,802.15. Status: Reported complete (DPWH). Contractor on record: R-II BUILDERS INC. Figures trace to dpwh.

Flood Control Management Cluster, Central Office
Region: Central Office

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱3.3B total · 0 flags

4. Implementation

Contract Amount

₱1,042,782,802.15

Progress

Reported complete (DPWH)

Start Date

December 12, 2019

Target End

September 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.